Member Information and Posts by PersonagrataWe have SIL-3 certified Honeywell Safety Manager installed at site. A total of 6 each SMs are installed in redundant configuration i.e on controller as well as I/O levels. Since commissioning we have been facing frequent I/O module failures.
Few days back we have had an incident due to which all console stations went blank and restored after 12 mins. Interestingly no changeover of Experion servers occurred and Consoles did not picked up data from Controllers directly as well.
We have C-300 based Experion DCS installed at our plant with FTE network. System comprised of redundant Experion Servers and multiple Experion consoles & flex stations.
Experion Server Failure and Redundant did not take up the operation
New Replies:
Thanks a lot everyone for your response. especially Sastry who helped me a lot to recover this...
Select Page: 1
Your use of this site is subject to the terms and conditions set forth under Legal Notices and the Privacy Policy. Please read those terms and conditions carefully. Subject to the rights expressly reserved to others under Legal Notices, the content of this site and the compilation thereof is © 1999-2013 Nerds in Control, LLC. All rights reserved.
Users of this site are benefiting from open source technologies, including PHP, MySQL and Apache. Be happy.
Fortune
"I'd give my right arm to be ambidextrous."