As long as the point of the line 0.9 pf is within the capability curves of your generator is perfectly ok.

Besides 0.9 pf lag means you are supplying some reactive power to the grid, which is usually desirable for the grid and for the generator itself, which has greater rotor magnetic field to cope against disturbances (overexcitation).
 